Pandora Production Office Building

  • Concentrate
  • Gamma Cure
  • Megamix II
  • Patch’n Plug
  • Wastewater Collection & Treatment
  • Water Holding Structures

The Pandora Production Company completed its new jewellery manufacturing and office development in April 2018. Administration and production floors cover 21,000m2, and house over 3000 employees.

The asset owners had specific requirements for the protection of the wastewater tanks, which are part of the production facilities in the jewellery manufacture. The harsh acidic environment in the waste tanks sustains consistent ph. 3-11 levels, which would severely reduce the service life of the structures, damaging the concrete matrix and accelerating corrosion of reinforcing steel work. Xypex Concentrate provides the necessary protection against these hazards, as the crystalline structure becomes an integral and permanent part of the structure.

Following casting, all the tanks were checked for minor defects and 750kg of our repair products (Xypex Patch’n Plug and Megamix II were used to prepare the substrates for the Xypex Concentrate coating system. In all, 4500m2 were successfully treated, ensuring the design service life, durability and impermeability to water factors were met.